APRC Propane Compressor Installation

  04-Sep-2018
APRC Propane Compressor Installation Eng. Amgad Al-Ahmady Mohamed, EPROM Chairman and CEO declared that EPROM Company had successfully completed the project of Construction of the new Propane Compressor, Auxiliary Skid, Accessories and its Sunshade - Unit 13A at APRC Company as per their request. He also said that the project was executed in professional manner without any delays and within budget achieving best quality without any accident or incidents.
The scope of work was the installation of a New Propane Compressor and the sun shade, installation of (EX) Overhead Crane Capacity 5 Ton and the construction of its control room and UPS as follows: Civil, Mechanical, Rotating and Electrical works including lighting and earthing Works.

Chairman& CEO confirmed that the project was completed successfully as per project schedule, from July 2017 till July 2018 according to Highest Levels of Standards, Quality & Safety manner that met all Clients’ requirements & needs.

Eng. Yehia Abdelkader, EPROM Chairman Assistant for Maintenance & Inspection and Project Director, stated that the installed compressor weightage is 35 Ton, the (EX) Overhead Crane capacity 5 Tons and project’s main activities such as Concrete foundation, steel structure, and electrical works were completed as per international Codes & Standards for such Project, Also he appreciates the team efforts since the preparation, planning till project Completion.

Project Team; Eng. Hisham El Deeb, Eng. Ahmed Mesbah, Eng. Ahmed Khalel
Eng. Hazem Yousry, Eng. Mohamed Abdel Rehim , Eng. Mohamed Masoud
Eng. Ayman Ezzat, Eng. Hafez Ahmed
Eng. Rania Alaa, Eng. Ahmed Abu Ouf
Mr. Ramy AbdEl-Karim
& Mr. Wael Hamad.


Project Highlights

Compressor 35 Ton
Overhead Crane (EX) type 5 Ton
Steel Structure 33 Ton
Concrete Works 237 m3
Sunshade 326 m2
Electrical Cabling works 850 m
Lighting “Cortem” EX Type 23
Earthing System Furse System