Construction of Fire Fighting 4th Stage Pipeline Project – APRC

  01-Aug-2017
Construction of Fire Fighting 4th Stage Pipeline Project – APRC Eng. Amgad Al-Ahmady Mohamed, Chairman and CEO of Egyptian Projects Operation and Maintenance (EPROM), stated that EPROM had completed successfully the “Construction of Fire Fighting 4th Stage Project “on August 2017.
The Project is 4 Km length, 21100 Dia. Inch EPROM scope was include all workshop and site welding activities, NDT, painting and sandblasting activities, Hydro test, pre-commissioning and commissioning activities such project was executed as per international standards that met Client (APRC) needs and requirements
Project Team; Eng. Ahmed Khalel, Eng. Ahmed Mesbah, Eng. Hazem Yousy, Eng. Mohamed Salah, Eng. Mohamed El Sharkawy, Eng. Hisham El Deeb, Eng. Ahmed Essam.